1.Understand the situation at the factory. (Hearing)

a) Wastewater volume per day (if there is a change with time, the amount of wastewater per hour)

b)About the main component contained in drainage. Heavy metal, oil etc.

c)factory operation time

d)Presentation of drainage numerical report from industrial estate

2.Collection of wastewater samples at the factory

3.In our laboratory, processing test of wastewater sample

Consideration of optimum treatment method and selection of coagulant
According to the provisional provision above, treated water is collected by a demonstration machine
Submit raw water at the factory and processed water samples at our laboratory to the inspection institution
COD, OIL, heavy metals etc are measured.

4.About the processing method, look at the inspection result sent from the inspection organisation
Confirm whether there is a problem. It was judged that there was no problem by our processing method
In case you enter the design of the drainage facility based on the given daily wastewater volume

5.Complete drainage processing flow, top view.

6.Based on the above flow, create a quotation and running cost table for one month.

7.Presentation at customer location

All of the above fees are free. . . (Cost at including inspection institution)